Full Capacity Underway – Prison Projects on site in 2026

by Megan Pounds

What the UK Infrastructure Strategy has in store for prison construction projects

Since the government’s UK Infrastructure Strategy has been announced, £6.3bn has been pledged to invest in prison expansion construction projects. The 10-year Prison Capacity Strategy has a goal of opening 14,000 spaces by 2031.

According to Barbour ABI planning data, there are 56 prison new build or extension construction projects already underway or set to begin in 2026 with a total value of £4.63bn.

Tier 1 contractor Kier has been noted to secure £250m worth of contracts under the Ministry of Justice’s Small Secure Houseblocks Programme (SSHP) Alliance. They are listed as the main contractor in many of the projects below. Wates and Laing O’Rourke have also been appointed within the Alliance to provide energy efficient and high value prisons.

Continue reading to discover just some of the prison projects we’re consistently tracking across the UK within the infrastructure sector.

 

HMP Glasgow Super Prison

HMP Glasgow Super Prison

The HMP Glasgow Super Prison in Strathclyde has been underway since March 2025 with Kier Scotland as the main contractor. The £998.4m project is due to be completed in September 2028.

The project consists of a new prison to hold 2000 inmates. The new build is replacing the previous Victorian-age prison, HMP Barlinnie, that was deemed no longer fit for purpose. View the project on the platform with Project ID: 12390481.

Client: Scottish Prison Services

Main Contractor: Kier Scotland

Planner: Cameron Planning

Architect: Pick Everard

Civil Engineer & Structural Engineer: Curtins Consulting Limited

Mechanical and Electrical Engineers: Halton Foodservice Limited, Arup Scotland

Groundworks contractors: Carey Group PLC, Statom Group Limited

Foundations Contractors: Carey Group PLC, Roger Bullivant Limited, Statom Group Limited, National Pile Croppers

M&E Subcontractor: FES Group

Need to see more roles and their contact information? Book a demo and reference Project ID: 12390481.

HMP Highland New Prison

HMP Highland New Prison

Balfour Beatty was appointed the main contractor and groundworks contractor in 2021 for the HMP Highland new build prison in Inverness. The £209.3m started in January of 2024 and is due to finish in autumn 2026. According to our platform the site progress is at 95%.

The project consists of a new prison with a capacity of 200 persons. It also comprises of an exercise yard, estates stores yard, house block zone, car park, and a facilities building. According to Balfour Beatty’s website, HMP Highland will be the first net zero prison in Scotland. View the project on the platform with Project ID: 12291271.

Client: Scottish Prison Services

Main Contractor: Balfour Beatty

Planner: Cameron Planning

Architect: BakerHicks

Civil Engineer: BakerHicks

Energy Consultant: Genius Energy Lab Limited

Groundworks contractors: UBCivils Limited, Balfour Beatty

Concrete frame subcontractor: FP McCann

M&E Subcontractor: G & A Barnie Group Limited

Steel Frame Subcontractors: Metaltech UK Limited, BSB Structural Limited

Need to see more roles and their contact information? Book a demo and reference Project ID: 12291271.

HMP Lancaster Farms – Two Housing Blocks

The HMP Lancaster Farms prison project is currently underway and is reported to be 65% of the way completed. Kier Northern is leading the £9.5m project as the main contractor. The project comprises of two housing blocks, a workshop, and a multi-use games area with associated works.

The project began in January 2025 and is due to finish September 2026. View the project on the platform with Project ID: 12721745.

Client: Ministry of Justice 

Main Contractor: Kier Northern

Planner: Cushman and Wakefield

Architect: Mace Limited

Landscape Architect: Fabrik Limited

Transport Consultant: Robert West Consulting

Groundworks contractors: Kiernan Construction Limited

Foundations Contractor: Bachy Soletanche Limited

Civils Contractor: A J Binns Limited

Need to see more roles and their contact information? Book a demo and reference Project ID: 12721745.

HMP Hindley – Accelerated Houseblock Programme 

Wates Construction was confirmed as the main contractor for the £40m HMP Hindley Accelerated Houseblock Programme project in October 2025. The project is due to start November 2026 and will take 36 months to complete with a project finish date of November 2029.

Comprising of a houseblock for up to 247 prisoners, the project also includes a gatehouse extension, segregation building extension, MUGA, and associated ancillary development.

View the project on the platform with Project ID: 12877585

Client: Ministry of Justice 

Main Contractor: Wates Construction Limited

Planner: Cushman and Wakefield

Architect: Baker Hicks Limited

Flood risk assessment consultant: Baker Hicks Limited

Need to see more roles and their contact information? Book a demo and reference Project ID: 12877585

HM Prison Grendon Springhill 2 

HM Prison Grendon Springhill 2

Due to have boots on site in Q3 2026, the Grendon Springhill 2 Prison project is valued at £300m. When completed it will be able to hold 1,500 inmates and will sit next to the existing HMP Springhill and HMP Grenon sites.  ISG was originally named as the main contractor on the project, but they have since filed for administration. Laing O’Rourke has been marked as the preferred bidder on our platform, they are also a part of the SSHB Alliance.

The project consists of a new prison with six houseblocks and supporting ancillary works.

View the project on the platform with Project ID: 12576965

Client: Ministry of Justice 

Preferred Bidder: Laing O’Rourke

Planner: Cushman and Wakefield

Architects: HLM Architects, Pick Everard

Project Manager: Mace Limited

Landscape architect: Pegasus Planning Group

Need to see more roles and their contact information? Book a demo and reference Project ID: 12576965

HMP Channings Wood New Housing Blocks 

Kier’s Western Limited branch is the main contractor for the HMP Channings Wood project consisting of new housing blocks. The project started in March 2025 and has a finish date of July 2027.

The whole project comprises of two 3-storey house blocks which will house an additional 494 prison places. Kier has stated that the project will also deliver two fully-electric and energy efficient X-shaped T60 houseblocks that support the MOJ’s commitment to reducing carbon emissions. These houseblocks were developed specifically for the Accelerated Houseblock Delivery Programme (AHDP) and have been used in other projects such as the HMP Elmley on the Isle of Sheppey in Kent.

The project also consists of one multi-use games area and pitch, workshop, prison store, and more.

View the project on the platform with Project ID: 12634121

Client: Ministry of Justice

Main Contractor: Kier Western Limited

Architect: AWW

Groundworks contractors: Churngold Construction, Hannafin Contractors Limited

External walls subcontractor: PCE Limited

Heating & Ventilation Subcontractor: Dodd Group Limited

Need to see more roles and their contact information? Book a demo and reference Project ID: 12634121

Accessing prison construction projects on Barbour ABI

If you’d like access to the hundreds of prison construction projects, and other infrastructure project leads, select the button below to request a demo.

We track all projects from refurbs, alterations, extensions, to new builds and more across all planning stages. Learn more about how our Construction Project Leads Platform can win you more work here.

About the author

Picture of Megan Pounds

Megan Pounds

Megan is an SEO Specialist with a knack for webpage and content production. She is a Marketing Manager within the Demand Generation Team and has a hand in campaign planning, managing, and execution. She has a background in product manufacturing and has been with Barbour ABI since 2023.

Recent News

Barbour ABI Blog

Categories:

Barbour ABI Blog

Categories:

Barbour ABI Blog

Categories:

Claim your 10 free project leads today

Get a free trial of the Barbour ABI platform

Simply fill in your details below and a member of our expert team will give you a call to arrange your trial.

Your data is protected by our privacy policy

Get your 10 free project leads today

Simply complete the form below and our team will be in touch to provide your 10 free leads, personally selected by our construction experts.

Your data is protected by our privacy policy

Is your 2026 sales strategy sorted yet?

Get a free 20 minute sales consultation with our expert team to:

  • Find out how Barbour ABI can help you source more target leads
  • Discover where your competitors are winning and losing
  • Build a strategy for success that works for your business

Set yourself up for success with Barbour ABI

Book your free 20-min consultation today:

  • Watch in real-time as our experts find live sales opportunities in your key markets
  • Seek out key target sectors or businesses to focus on this year
  • Understand where your competitors are winning and what you can do about it
  • Build a strategy for success that works for your business

Book a Demo

Helping Contractors

Win More Business

Get in touch with us and see how we can help you win more work.

FIND YOUR

10 FREE

PROJECT LEADS TODAY

Barbour ABI White Logo

Place of registration: Barbour ABI Limited Company number: 13427982, Registered office: 5th Floor, 133 Houndsditch, London, EC3A 7BX