Top 10 Contractors Working on Data Centre Construction Projects UK

by Megan Pounds

As data centre construction continues to surge, Barbour ABI is monitoring the top construction companies working on these projects across the UK. 

At the time of this blog’s publication, we can confirm there are 22 data centre projects with contractors appointed that are due to finish in the next two years. View the contractors working on these projects in the table below and additional project information further down the page. All projects can be found on our Construction Project Leads Platform.

Top 10 Contractors working on Data Centre Construction Projects

Position Contractor Project Value Finish Date View Project
1 TSL Projects Saunderton Data Centre – 4 Virtus Data Centres £500m Jul-26 View Project
2 Yondr Group Limited Former Akzo Nobel Site Phase 1 – Building C, Data Centre £400m Sep-27 View Project
3 John Paul Construction Microsoft – Imperial Park Data Centre £400m Jan-27 View Project
4 Laing O’Rourke Delivery Limited Slough Trading Estate – LD14 Data Centre £300m Sep-26 View Project
5 JCA Engineering Limited KAO Data Campus – KLON-03 – Data Centre £175m Q4 2026 View Project
6 Skanska Telehouse South Main Works – Refurbishment £158m Sep-27 View Project
7 Sewell Group Yorkshire Energy Park Phase 1 – 13.5MW Energy Centre and Data Centre £125m Aug-26 View Project
8 Keysource Limited Deep Green Technologies Limited, Urmston – Data Centre £20m Apr-26 View Project
9 Sudlows Limited St Michaels Road – Data Centre £2.6m Jul-26 View Project
10 SDC Construction Group Aston Martin F1, Silverstone – Data Centre £1.2m Aug-26 View Project

Saunderton Data Centre – 4 Virtus Data Centres

The project consists of an office accommodation to form data centres to house critical IT systems data centres capable of delivering IT capacity of 75MW with staff facilities including car parking, ancillary plant and electricity sub stations on site, following demolition works.

Contractor: TSL Project 

Location: Buckinghamshire

Value: £500m

Project ID: 10234430

Start Date: 20-Jan-2025

Finish: 16-Jul-2026

Saunderton Data Centre – 4 Virtus Data Centres

Slough Trading Estate – LD14 Data Centre

Erection of a 5 storey 30MW data centre with associated offices, landscaping, access and parking.

Contractor: Laing O’Rourke Delivery Limited

Location: Slough

Value: £300m

Project ID: 12685382

Start Date: December 2024

Finish: September 2026

KAO Data Campus – KLON-03 – Data Centre

Construction of a new 17.6MW Data Centre.

Contractor: JCA Engineering Limited

Location: Essex

Value: £175m

Project ID: 12839274

Start Date: March 2024

Finish: Q4 2026

KAO Data Campus – KLON-03 – Data Centre

Telehouse South Main Works – Refurbishment

Refurbishment of existing data centre facility replacement roof-top plant new façade treatment.

Contractor: Skanska

Location: London

Value: £158m

Project ID: 12647502

Start Date: June 2024

Finish: September 2027

Yorkshire Energy Park Phase 1 – 13.5MW Energy Centre and Data Centre

13.5MW energy centre and a Tier 3 data centre with access and landscaping works.

Contractor: Sewell Group

Location: East Riding of Yorkshire

Value: £125m

Project ID: 12628941

Start Date: January 2024

Finish: August 2026

Yorkshire Energy Park

Microsoft – Imperial Park Data Centre

Erection of data centre following demolition of existing building.

Contractor: John Paul Construction

Location: Newport

Value: £400m

Project ID: 12673794

Start Date: February 2025

Finish: January 2027

Microsoft Imperial Park Data Centre

Former Akzo Nobel Site Phase 1 – Building C, Data Centre

Erection of 40MW data centre comprising of 4 10MW data halls, offices, loading bays, technical rooms, external plant gantries all with associated parking, access and landscaping.

Contractor: Yondr Group Limited

Location: Slough

Value: £400m

Project ID: 12778797

Start Date: November 2025

Finish: September 2027

Deep Green Technologies Limited, Urmston – Data Centre

Erection of a data centre facility and associated plant and enclosure. Converted to heat energy for the leisure centre to use free of charge.

Contractor: Keysource Limited

Location: Greater Manchester

Value: £20m

Project ID: 12801528

Start Date: July 2025

Finish: April 2026

St Michaels Road – Data Centre

Construction of a data centre, external plant and machinery with boundary treatments, landscaping and associated works.

Contractor: Sudlows Limited

Location: Hampshire

Value: £2.6m

Project ID: 12816266

Start Date: April 2026

Finish: July 2026

Aston Martin F1 – Silverstone – Data Centre Project

Erection of a data centre facility, including bridge link, landscaping and associated works for Aston Martin Formula One Team following demolition.

Contractor: SDC Construction Group

Location: Towcester

Value: £1.2m

Project ID: 12867466

Start Date: August 2026

Finish: June 2027

Aston Martin Data Centre

How can I find Data Centre Projects on Barbour ABI? 

Clients can find data centre projects using the Construction Project Leads Platform’s advanced search options. 

On our AI Search, type in the following prompt:

Show data centre projects due to finish in the next two years. Only show projects that are assigned a contractor

On our filtered search check the following:

Project search: Data centre

Categories: High-tech offices, Warehouses & storage buildings

Project Timeline: Construction will end between today or 2 years in the future

Stages: Main Contract Awarded

Not a client? No worries, get in touch today and we’ll be happy to share more details about our data centre and other industrial and infrastructure construction project leads. 

About the author

Picture of Megan Pounds

Megan Pounds

Megan is a Demand Generation Marketing Manager who specialises in SEO, campaign management, webpage design, and graphic design. She has a background in product manufacturing in both building materials and powdered metal. Megan has been with Barbour ABI since 2023.

Recent News

Barbour ABI Blog

Design Tenders Set to Dive In for Only Rainwater into Windermere Project

Categories:

Barbour ABI Blog

Barbour ABI Training Room: How to use our AI-search

Categories:

Barbour ABI Blog

£771m in Awards for AMP8 Water Infrastructure Projects

Categories:

Claim your 10 free project leads today

Get your 10 free project leads today

Simply complete the form below and our team will be in touch to provide your 10 free leads, personally selected by our construction experts.

Your data is protected by our privacy policy

Set yourself up for success with Barbour ABI

Book your free 20-min consultation today:

  • Watch in real-time as our experts find live sales opportunities in your key markets
  • Seek out key target sectors or businesses to focus on this year
  • Understand where your competitors are winning and what you can do about it
  • Build a strategy for success that works for your business

Book a Demo

Helping Contractors

Win More Business

Get in touch with us and see how we can help you win more work.

FIND YOUR

10 FREE

PROJECT LEADS TODAY

Barbour ABI White Logo

Place of registration: Barbour ABI Limited Company number: 13427982, Registered office: 5th Floor, 133 Houndsditch, London, EC3A 7BX